Old 12-27-06, 04:01 PM   #1
N_C
Banned.
Thread Starter
 
N_C's Avatar
 
Join Date: Oct 2002
Location: Bannation, forever.
Bikes:
Posts: 2,887
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
Is it me or are construction costs increasing?

It seems that the cost of construction is increasing. I know it happens with an increase of materials, labor, etc., but it seems lately it has gone up incredibly high.

Could it be because contractors are spending more time then they want doing trail construction projects instead of the jobs they want to do & make more money on, like roadways, etc. so they have increased the costs? Or do you think it is just the "natural" progression of the increase of things like trail construction? Or do you think it is because of something else?

Or am I way off base here & the costs are actually not that bad at all & have hardly increased?

Here are some links showing the costs of current & proposed projects:

http://www.bikeiowa.com/asp/hotnews/...sp?NewsID=1923

http://www.bikeiowa.com/asp/hotnews/...sp?NewsID=1931

http://www.bikeiowa.com/asp/hotnews/...sp?NewsID=1928
N_C is offline   Reply With Quote
Old 12-27-06, 04:07 PM   #2
CrosseyedCrickt
Banned.
 
Join Date: Jun 2006
Location: I've had enough.
Bikes:
Posts: 898
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
is it me, or does every post you make have a bikeiowa link in it
CrosseyedCrickt is offline   Reply With Quote
Old 12-27-06, 04:10 PM   #3
timmhaan
more ape than man
 
timmhaan's Avatar
 
Join Date: Nov 2003
Location: nyc
Bikes:
Posts: 8,093
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
the price of projects around here are astronomically high. it's hard to grasp when even the smallest thing is millions or tens of millions of dollars. i don't really know how my tax dollars are being used or if we're all being taking for a ride (no pun intended).
timmhaan is offline   Reply With Quote
Old 12-27-06, 05:20 PM   #4
genec
genec
 
genec's Avatar
 
Join Date: Sep 2004
Location: West Coast
Bikes: custom built, sannino, beachbike, giant trance x2
Posts: 24,692
Mentioned: 3 Post(s)
Tagged: 0 Thread(s)
Quoted: 290 Post(s)
The cost of fuel and labor has been regularly increasing, and the cost of concrete has gone up quite a bit due to a strong demand for the raw materials from China.
genec is offline   Reply With Quote
Old 12-27-06, 08:27 PM   #5
derath
Senior Member
 
Join Date: Dec 2005
Location: Reisterstown, MD
Bikes:
Posts: 3,190
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 2 Post(s)
Quote:
Originally Posted by CrosseyedCrickt
is it me, or does every post you make have a bikeiowa link in it

At least this time he said something. Usually it is just a post with the link and no explanation.

FWIW, costs have increased. Increased fuel costs for all the machinery. Anything asphalt costs more (asphalt=oil). Many other building material costs have been skyrocketing in recent years.

-D
derath is offline   Reply With Quote
Old 12-27-06, 09:21 PM   #6
Tom Stormcrowe
Out fishing with Annie on his lap, a cigar in one hand and a ginger ale in the other, watching the sunset.
 
Tom Stormcrowe's Avatar
 
Join Date: Mar 2006
Location: South Florida
Bikes: Techna Wheelchair and a Sun EZ 3 Recumbent Trike
Posts: 16,120
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
Quote:
Originally Posted by CrosseyedCrickt
is it me, or does every post you make have a bikeiowa link in it
Nothing wrong with that...if you don't want to read the linked material, don't make with the click, it's as simple as that!
__________________
. “He who fights with monsters might take care lest he thereby become a monster. And if you gaze for long into an abyss, the abyss gazes also into you.”- Fredrick Nietzsche

"We can judge the heart of a man by his treatment of animals." - Immanuel Kant
Tom Stormcrowe is offline   Reply With Quote
Old 12-28-06, 12:24 AM   #7
oboeguy
34x25 FTW!
 
oboeguy's Avatar
 
Join Date: Sep 2004
Location: NYC
Bikes: Kona Jake, Scott CR1, Dahon SpeedPro
Posts: 6,013
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
Quote:
Originally Posted by timmhaan
the price of projects around here are astronomically high. it's hard to grasp when even the smallest thing is millions or tens of millions of dollars. i don't really know how my tax dollars are being used or if we're all being taking for a ride (no pun intended).
No kidding. It seems like a half mile stretch of Greenway would cost millions. Crazy
oboeguy is offline   Reply With Quote
Old 12-28-06, 08:31 AM   #8
wahoonc
Senior Member
 
wahoonc's Avatar
 
Join Date: Jan 2005
Location: On the road-USA
Bikes: Giant Excursion, Raleigh Sports, Raleigh R.S.W. Compact, Motobecane? and about 20 more! OMG
Posts: 16,687
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 1 Post(s)
The costs don't look to be way out of line for what is being done. Those costs will include the engineering, development of standards (if they don't already exist) and the necessary oversight and management. Also small projects like a trail tend to have higher per unit cost than say a street repaving project due to restricted access and the additional labor involved. As an example, it costs my company just as much to set up and provide basic administration for a $50,000 project as it does for a $500,000 project. Also many companies are not set up to handle a narrow paving project like a trail, so you have a more limited number of bidders.

Aaron
__________________
Webshots is bailing out, if you find any of my posts with corrupt picture files and want to see them corrected please let me know. :(

ISO: A late 1980's Giant Iguana MTB frameset (or complete bike) 23" Red with yellow graphics.

"Cycling should be a way of life, not a hobby.
RIDE, YOU FOOL, RIDE!"
_Nicodemus

"Steel: nearly a thousand years of metallurgical development
Aluminum: barely a hundred
Which one would you rather have under your butt at 30mph?"
_krazygluon
wahoonc is offline   Reply With Quote
Old 12-28-06, 09:00 AM   #9
Roughstuff
Punk Rock Lives
 
Roughstuff's Avatar
 
Join Date: Feb 2002
Location: In a cabin in the adirondacks
Bikes: Fuji touring
Posts: 3,080
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 12 Post(s)
Quote:
Originally Posted by timmhaan
the price of projects around here are astronomically high. it's hard to grasp when even the smallest thing is millions or tens of millions of dollars. i don't really know how my tax dollars are being used or if we're all being taking for a ride (no pun intended).

Most states have rules that require public projects to pay the union wage for construction workers, even when non-union labor is employed. Sort of like forcing people to grocery shop in the gourmet food section only. That, and the tangle of safety and environmental regulations, and before ya know it, pop goes the weasel.

And politicians are weasels already...

roughstuff
Roughstuff is offline   Reply With Quote
Old 12-28-06, 01:12 PM   #10
jimmuter
Urban Biker
 
jimmuter's Avatar
 
Join Date: Aug 2005
Location: Durham, NC
Bikes: Trek 720 hybrid; 2007 Specialized Tricross Comp
Posts: 731
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
Concrete, glass, steel, etc. - it's all gone up a lot. Our costs escalate about 1% per month at the moment. It's also difficult, as someone else mentioned, to get these types of projects bid on. It's best if they can be bundled for a single contractor. There are a lot of costs that go beyond construction as wahoonc showed above. You may also need to factor in the cost of land acquisition in many cases. Don't even ask about the costs for recruiting minority-owned firms to satisfy quotas set by politicians.
jimmuter is offline   Reply With Quote
Old 12-28-06, 02:08 PM   #11
avmanansala
Senior Member
 
avmanansala's Avatar
 
Join Date: Aug 2006
Location: Sacramento, CA
Bikes: Cannondale Road Warrior
Posts: 401
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
There are several reasons for the increased cost in construction lately but the single biggest factor that I've heard is the cost of materials; a lot of that started with the reconstruction after hurricane Katrina; then of course, there is the construction in Iraq; China and their boom in prep for the Olympics... Many contractors right now are increasing their bids on my government projects, too.

You'd be outraged if I told you the square foot estimates that my department is using on some of the facilities that we design (I work for a state agency).

Somebody somewhere is definately making a fortune and taxpayers are foot with the bill!
avmanansala is offline   Reply With Quote
Old 12-29-06, 09:21 PM   #12
ken cummings
Senior Member
 
ken cummings's Avatar
 
Join Date: Dec 2005
Location: northern California
Bikes: Bruce Gordon BLT, Cannondale parts bike, Ecodyne recumbent trike, Counterpoint Opus 2, miyata 1000
Posts: 5,601
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
The biggest jump in costs around here is for aggregate. The stream gravel or crushed rock used for concrete, asphalt paving, and trail/road base. The main and inexpensive source was from a river that also carried spawning "endangered" fish. Scratch that source. Now we use rock from 6 local quarries, several regional quarries, and some rock shipped over 1,000 miles from Canada. And, people around most of the quarries are fighting the increased truck traffic.
ken cummings is offline   Reply With Quote
Old 12-31-06, 12:29 AM   #13
Midnight Cyril
Senior Member
 
Join Date: Sep 2006
Bikes:
Posts: 88
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 0 Post(s)
Quote:
Originally Posted by N_C
Could it be because contractors are spending more time then they want doing trail construction projects instead of the jobs they want to do & make more money on, like roadways, etc. so they have increased the costs?
Nope. Construction costs are rising across the board. Not evenly, perhaps, but that'll be due to markets for particular material and labor.
Midnight Cyril is offline   Reply With Quote
Old 12-31-06, 07:13 PM   #14
bkaapcke
Senior Member
 
Join Date: Jul 2005
Bikes:
Posts: 3,226
Mentioned: 0 Post(s)
Tagged: 0 Thread(s)
Quoted: 6 Post(s)
The dollar is no good when it comes to paying for real things or real work. Then there is the insurance, taxes workmans comp, and on and on. Right here in the bay aea we're spending billions on a new bridge. Retrofitting for earthquake safety would be far cheaper, but Caltrans wanted to build a new bridge. So they lied about how expensive retrofitting would be and about how cheap the new bridge would be. The powers that be bought into it long enough that they couldn't get out. Now we're stuck. Why, on rereading this mini rant, I realized it sounds just like Iraq. So much for accountability. bk
bkaapcke is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT -6. The time now is 11:01 AM.