Track Cycling: Velodrome Racing and Training Area - Cleveland Velodrome

Bikeforums.net is a forum about nothing but bikes. Our community can help you find information about hard-to-find and localized information like bicycle tours, specialties like where in your area to have your recumbent bike serviced, or what are the best bicycle tires and seats for the activities you use your bike for.
Speedskater
05-09-12, 10:16 AM
Any more information on this Cleveland Velodrome?
"Olympic-style Velodrome Coming to Slavic Village"
http://www.coolcleveland.com/blog/2012/04/olympic-style-velodrome-coming-to-slavic-village/
carleton
05-09-12, 10:38 AM
Any more information on this Cleveland Velodrome?
"Olympic-style Velodrome Coming to Slavic Village"
http://www.coolcleveland.com/blog/2012/04/olympic-style-velodrome-coming-to-slavic-village/
Cleveland-based nonprofit Fast Track Cycling has signed a purchase contract and ground lease to bring a 166-meter steel and wood velodrome to Slavic Village. A groundbreaking ceremony will be held Tue 5/1 @ 2PM and the track is slated to open on Sat 6/16.
Sigh.
Flatballer
05-09-12, 06:28 PM
Wait, it's gonna be built in just 6 weeks or something? That's crazy. I guess 166m is better than nothing.
Also, 166m does not an Olympic style velodrome make.
carleton
05-09-12, 10:05 PM
The website says that it will be identical to the track in Chicago. Here is the track in Chicago:
http://www.youtube.com/watch?v=pzLhMo44Ngw
David Broon
05-11-12, 12:00 AM
I feel like the transitions must be brutal if you're out of the sprinters lane.
Looks like Dale is doing another short track. His short tracks (like Chicago) are portable and take a few weeks for final assembly the first time. After that it takes about a day or two to assemble.
Speedskater
05-11-12, 12:47 PM
The construction schedule on the lower part of the page:
http://clevelandvelodrome.org/volunteer-for-construction/
What dates - starting May 14th - can you help us construct the velodrome? * Select days that apply. Thanks!
5/14/2012 - Day 5 - Erecting steel trusses
5/15/2012 - Day 6 - Erecting steel trusses
5/16/2012 - Day 7 - Erecting steel trusses
5/17/2012 - Day 8 - Erecting steel trusses
5/18/2012 - Day 9 - Erecting steel trusses
5/19/2012 - Day 10 - Erecting steel trusses
5/20/2012 - Day 11 - Installing & welding the ribs to the trusses
5/21/2012 - Day 12 - Installing & welding the ribs to the trusses
5/22/2012 - Day 13 - Installing & welding the ribs to the trusses
5/23/2012 - Day 14 - Installing & welding the ribs to the trusses
5/24/2012 - Day 15 - Installing & welding the ribs to the trusses
5/25/2012 - Day 16 - Surface installation
5/26/2012 - Day 17 - Surface installation
5/27/2012 - Day 18 - Surface installation
5/28/2012 - Day 19 - Surface installation
5/29/2012 - Day 20 - Surface installation
5/30/2012 - Day 21 - Surface installation
5/31/2012 - Day 22 - Surface installation
6/1/2012 - Day 23 - Surface installation
6/2/2012 - Day 24 - Surface installation
6/3/2012 - Day 25 - Surface installation
6/4/2012 - Day 26 - Apron installation
6/4/2012 - Day 27 - Apron installation
6/5/2012 - Day 28 - Apron installation
6/6/2012 - Day 29 - Apron installation
6/7/2012 - Day 30 - Apron installation
6/8/2012 - Day 31 - Guard rail, painting lines
6/9/2012 - Day 32 - Guard rail, painting lines
6/10/2012 - Day 33 - Guard rail, painting lines
6/11/2012 - Day 34 - Guard rail, painting lines
6/12/2012 - Day 35 - Guard rail, painting lines
Speedskater
05-14-12, 05:28 PM
I stopped by the track site today. The first shipment of components arrived and the are getting organized for construction.
http://clevelandvelodrome.org/
Powered by vBulletin® Version 4.1.12 Copyright © 2013 vBulletin Solutions, Inc. All rights reserved.