The construction schedule on the lower part of the page:
http://clevelandvelodrome.org/volunt...-construction/
What dates - starting May 14th - can you help us construct the velodrome? * Select days that apply. Thanks!
- 5/14/2012 - Day 5 - Erecting steel trusses
- 5/15/2012 - Day 6 - Erecting steel trusses
- 5/16/2012 - Day 7 - Erecting steel trusses
- 5/17/2012 - Day 8 - Erecting steel trusses
- 5/18/2012 - Day 9 - Erecting steel trusses
- 5/19/2012 - Day 10 - Erecting steel trusses
- 5/20/2012 - Day 11 - Installing & welding the ribs to the trusses
- 5/21/2012 - Day 12 - Installing & welding the ribs to the trusses
- 5/22/2012 - Day 13 - Installing & welding the ribs to the trusses
- 5/23/2012 - Day 14 - Installing & welding the ribs to the trusses
- 5/24/2012 - Day 15 - Installing & welding the ribs to the trusses
- 5/25/2012 - Day 16 - Surface installation
- 5/26/2012 - Day 17 - Surface installation
- 5/27/2012 - Day 18 - Surface installation
- 5/28/2012 - Day 19 - Surface installation
- 5/29/2012 - Day 20 - Surface installation
- 5/30/2012 - Day 21 - Surface installation
- 5/31/2012 - Day 22 - Surface installation
- 6/1/2012 - Day 23 - Surface installation
- 6/2/2012 - Day 24 - Surface installation
- 6/3/2012 - Day 25 - Surface installation
- 6/4/2012 - Day 26 - Apron installation
- 6/4/2012 - Day 27 - Apron installation
- 6/5/2012 - Day 28 - Apron installation
- 6/6/2012 - Day 29 - Apron installation
- 6/7/2012 - Day 30 - Apron installation
- 6/8/2012 - Day 31 - Guard rail, painting lines
- 6/9/2012 - Day 32 - Guard rail, painting lines
- 6/10/2012 - Day 33 - Guard rail, painting lines
- 6/11/2012 - Day 34 - Guard rail, painting lines
- 6/12/2012 - Day 35 - Guard rail, painting lines